The graphic below represents the broad progess of the PE
AK Project Financials implementation. Roll your cursor over a box to see details. Click on the box to see target dates and deliverables for each milestone within that phase, or select from the menu below:

planning Planning
construct Construct
transition Transition
deployment Deployment

To see the Detailed Project Plan, click here

Deployment (Fall '01)
Transition (Summer '01)
Construct (Spring '01)
Planning (Complete)

up

Financials Project Milestones

Planning
Milestone
Target Date
Deliverables
Initiate project Spring '98 Project started
Evaluate software Sum '99 Task complete
Complete needs assessment Sum '99 Task complete
Negotiate contract Spring '00 Signed contract
Initial planning meeting Sum '00 Planning workshop complete
Development system installed Sum '00 Development system in place
Publish project charter Fall '00 Final version of project charter
Define technical infrastructure Fall '00 Document complete
Complete project plan Fall '00 Project plan to EVP/COO
Complete communications plan Fall '00 Publish to community

up

Construct
Milestone
Target Date
Deliverables
Communicate project information Fall '00 Deliver to campus community
Project team training - Phase I Fall '00 Task complete
Complete draft Chart of Accounts Fall '00 Publish to community
Complete fit/gap analysis Fall '00 Publish to community
Plan for HR System Win '00 Complete workshop
Complete conversion Strategy Win '00 Present to key users
Complete prototyping/design Spring '01 Financial system configured for Brandeis business practices
up


Transition
Milestone
Target Date
Deliverables
Production system installed Spring '01 Production system in place
Complete documentation Spring '01 Publish to community
Complete cut-over preparation Spring '01 Publish to community
Plan for Finance Phase II Spring '01 Complete one day workshop
Complete system test & reports Sum '01 Task complete
Review project funding Sum '01 Report to EVP/COO
Complete performance test Sum '01 Task complete
up


Deployment
Milestone
Target Date
Deliverables
Complete end-user training Sum '01 Task complete
Complete cutover Sum '01 PeopleSoft environment ready for production data
Central administrative departments deployment Sum '01 First rollout complete
Go live Sum '01 Yea!
Complete Phase I Fall '01 Task complete