Brandeis PEAK Project
Quality Assurance Plan
Introduction
Process
System Tests
Parallel Tests
Quality Assurance Sessions
Budget
Project Plan
Communication Plan
Issues Log Document
Fit/Gap Document
Data-Mapping Documents
Functional Requirement Documents
Technical Requirement Documents
Programming Code Walk Throughs
Unit Tests
Procedural Documentation
Training Materials
Systems Tests
Parallel Tests
"Go No-Go" Decision
Cutover Plan
Post-Implementation Review
up

Click here to access a printable Adobe Acrobat .pdf file of this Quality Assurance Plan Document.
Get Adobe Acrobat Reader - needed to view this pdf file,


Introduction

This Quality Assurance Plan is intended to:
Ensure that all steps of the project are monitored.
Ensure proper user acceptance criteria for each type of testing.
Determine signoff procedures for various milestones.of certain data elements.
up
Process
We will maintain quality assurance through testing, correction, re-testing, and review sessions. Although the bulk of the QA work will take place in the review sessions, before that happens we will conduct system tests and parallel tests.

System Tests
For system testing:
Functional staff scripts and conducts system tests.
Technical staff makes programming changes.
Functional staff correct tables.
Integration testing management reviews system test results.
Up

Parallel tests
For parallel testing:
Functional and technical staff script and conduct parallel tests.
Technical staff makes programming changes.
Functional staff correct tables.
Functional and technical staff perform re-testing.
determine necessary interfaces.
Parallel tests:
Use converted data--automated and manual--to include interfaces in and out of system, most reports, and security setup.
Simulate of varying processes and period ends.


Quality Assurance Sessions
The Quality Assurance process will continue in the following sessions:

Budget
The project director, monitored by the steering committee, reviews the budget for:
cost overrun potential, and
actual versus budgeted dollars to date.
Up

Project Plan
The project team and the steering committee, monitored by project management, review the project plan:
to ensure milestone dates are on target,
for any changes in scope, and
for possible trouble spots.


Communication Plan
The communication plan, is reviewed (monitored by the steering committee) to:
ensure that key dates are on target,
ensure that communications are effective, and to
alert the team to changes of scope.
NOTE: The Project Plan reviewer needs to be determined.
Up

Issues-Log Document
The project team and the steering committee, monitored by project management, review the log document to ensure that:
target dates for resolution are being met,
high priority items are being resolved, and
the project is not in jeopardy.


Fit/Gap Document
The project team reviews the fit gap document for
completeness,
scope of changes,
conversion items,
interface items,
processes to be implemented,
Users sign off.
Up

Data-mapping Documents
Functional and technical staff review the data mapping documents for completeness. Users sign off.


Functional Requirement Documents
Functional and technical staff review the functional requirement documents. Users sign off.


Technical Requirement Documents
Functional and technical staff review the technical requirement documents. Users and technical manager sign off.


Programming Code Walk Throughs
Technical staff review programming code walk throughs. The technical manager signs off.


Unit Tests
Functional staff review and sign off on unit tests.


Procedural Documentation
Functional and technical staff review procedural documentation. The functional/technical manager signs off.
Up

Training Materials
Functional managers review and sign off on training materials.


Systems Tests
Integration testing management reviews system tests. Functional staff signs off.


Parallel Tests
Parallel testing management reviews parallel tests. Functional staff signs off.


"Go No-Go" Decision
The entire team reviews all aspects of the implementation to determine readiness to continue. This review examines:
the results of all testing,
security readiness,
hardware readiness,
network readiness,
database readiness, and
production readiness.
On completion, the project management writes their recommendation for approval by the steering committee.
Up

Cutover Plan
A committee of the project team will write the cutover plan. The team will review the plan to be sure it documents every step of the cutover. Project management will approve the plan and submit it to the steering committee to sign off.


Post-Implementation Review
The post implementation review documents what we did right and wrong, and what we will improve. This will prove particularly useful when it is referred to in later phases of this project.
up