home about for users for the team

Student Administration Project

Scope

Student Administration Project Scope

In order to most efficiently achieve the Student Administration project objectives, the project scope has been selected based on costs, benefits, and risks.

All proposed changes to project scope must follow the Change Request process outlined in this document


Phase 1 (to "initial live date") in scope

Business Process and Software Analysis


PeopleSoft Student Administration Modules

The scope list below represents items scheduled for technical implementation only. Some of these items may not be utilized by the user community immediately or at all.


Housing Solution

During the initial weeks of the project, the Core Team will determine the specifications for a tool to support the housing process.


Security


Reporting


Testing


Education Services


Interfaces

During the first few months of the project, the Core Team will perform an assessment of many of the university's systems to determine which systems will ultimately need to interface with the PeopleSoft Student Administration system. Each system will be categorized as:

  1. Requiring an interface to go live;
  2. Requiring an interface, but not necessarily before live; or
  3. Not requiring an interface.

The assessment of systems for potential interfaces will include the following among others:


Historical Data Conversions

Data included in historical conversion will include:

  1. Student Records Data
  2. Student Accounts Data
  3. Student Financial Aid Data
  4. Student Admissions Data

During the initial months of the project, the Core Team will analyze various options for the detail specifications of the historical data conversions. The analysis will include:

  1. Identifying the options for converting historical data into the PeopleSoft system;
  2. Understanding the business and technical implications of each option; and
  3. Determining a course of action.

Once the Core Team determines a course of action, it will implement the conversions and work with the involved groups to update business processes accordingly.


Potential future scope after Phase 1


Out of scope

Brandeis and Academe Roles and Responsibilities

The following table delineates activities by the Brandeis Student Administration Team, other Brandeis constituents, and Academe.


Brandeis SA Team Academe Brandeis Non-SA
Fit-gap analysis for "Phase 1 in scope" items
X X
PeopleSoft setup for "Phase 1 in scope" items
X X
Conversions from Legacy Systems to PeopleSoft Student Administration
X X
PeopleSoft Student Administration Security
X X
Reports
X X
Testing
X X
Business Process Redesign
X X
Business Process Documentation
X X
Support for legacy systems


X
Modifications to legacy systems


X
Approved PeopleSoft Patches and Updates
X

Approved modifications to PeopleSoft Student Administration
X X
Unapproved modifications, patches, or updates to PeopleSoft Student Administration
Out of Scope
Database Administration
X

Networks and Servers
X

End User Training
X X
Project Management and Communications
X