New Residence Hall Project Schedule

December 2000

Commence Programming

Chan Krieger

January 2001

Commence Design Team Selection Process

Campus Operations

February 2001

Complete Program (Site, Schedule, Budget)

Chan Krieger

March 2001

Authorize Initial Design Funds

Trustees

March 2001

Identify Client Team Members

Student Life

April 2001

Select Design Team

Project Committee

April 2001 Start Schematic Design Process Architect
June 2001 Complete Schematic Design Architect
October 2001 Authorize Project Trustees
October 2001 Complete Design Development Architect
February 2002 Bid/Negotiate Price (GMP) Project Manager
March 2002 Secure Approvals and Permits Architect / Project Manager
April 2002 Complete Construction Documents Architect
May 2002 Start Building Construction Construction Manager
June 2003 Complete Construction and Punchlist Construction Manager
July 2003 Complete Fitout (Furniture, Equipment) Construction Manager
August 2003 Occupy Completed Facility Brandeis

  
Return to Image Index
 

 
TOP

Home  ::  Overview  ::  Steering Committee  ::  Master Planning Scope

Images, Charts, and Lists  ::  Documents  ::  Master Planning Team and Consultants  ::  History

Suggestion Box

Brandeis University Home

 
This site is maintained by
the Office of the Executive VP/COO.
Comments and suggestions are welcome.