December 2000 |
Commence Programming |
Chan Krieger |
|
January 2001 |
Commence Design Team Selection Process |
Campus Operations |
|
February 2001 |
Complete Program (Site, Schedule, Budget) |
Chan Krieger |
|
March 2001 |
Authorize Initial Design Funds |
Trustees |
|
March 2001 |
Identify Client Team Members |
Student Life |
|
April 2001 |
Select Design Team |
Project Committee |
| April 2001 |
Start Schematic Design Process |
Architect |
| June 2001 |
Complete Schematic Design |
Architect |
| October 2001 |
Authorize Project |
Trustees |
| October 2001 |
Complete Design Development |
Architect |
| February 2002 |
Bid/Negotiate Price (GMP) |
Project Manager |
| March 2002 |
Secure Approvals and Permits |
Architect / Project Manager |
| April 2002 |
Complete Construction Documents |
Architect |
| May 2002 |
Start Building Construction |
Construction Manager |
| June 2003 |
Complete Construction and
Punchlist |
Construction Manager |
| July 2003 |
Complete Fitout (Furniture,
Equipment) |
Construction Manager |
| August 2003 |
Occupy Completed Facility |
Brandeis |